In 2005, Welch Comer assisted the City of Post Falls with the design and construction phase services of the Highway 41 sanitary sewer interceptor. This $1.9 million construction project was financed through a local improvement district, for which Welch Comer also assisted with the LID formation and confirmation process.

KEY ELEMENTS

  • Construction of 3.5 miles of 15” to 18” Diameter Pipeline
  • Completed on-time
  • Completed 24% under the original LID budget
  • Acquisition of Easements and Right-of-Way permits

 

Sewer Mainline was constructed at depths greater than 20 feet.

 

Utility coordination was a key design element.